Case Details
Naturgy Energy Group, S.A. and Naturgy Electricidad Colombia, S.L. (formerly Gas Natural SDG, S.A. and Gas Natural Fenosa Electricidad Colombia, S.L.) v. Republic of Colombia (ICSID Case No. UNCT/18/1)
-
Electrical power distributor
-
Electric Power & Other Energy
-
BIT Colombia - Spain 2005
-
UNCITRAL
-
Naturgy Energy Group, S.A. (formerly Gas Natural SDG, S.A.) (Spanish), Naturgy Electricidad Colombia, S.L. (formerly Gas Natural Fenosa Electricidad Colombia, S.L.) (Spanish)
-
Republic of Colombia (Colombian)
-
Stephen L. DRYMER (Canadian) - Appointed by Other
-
Eric SCHWARTZ (French, U.S.) - Appointed by the Claimant(s)
Alexis MOURRE (French) - Appointed by the Respondent(s) -
Three Crowns, London, U.K.
-
Agencia Nacional de Defensa Jurídica Internacional, Bogota, Colombia
Stanimir A. Alexandrov, Washington, D.C., U.S.A.
Sidley Austin, Washington, D.C., U.S.A. -
English,Spanish
-
Concluded
-
March 12, 2021 - The Tribunal renders its award.
(a) Original Proceeding
Composition of Tribunal
Party Representatives
No References Available.
(a) Original Proceeding
Date | Development |
---|---|
December 19, 2017 | The Tribunal is constituted in accordance with the UNCITRAL Arbitration Rules (1976). Its members are: Stephen L. Drymer (Canadian), President, appointed by the appointing authority, Eric A. Schwartz (French/U.S.); appointed by the Claimants; and Alexis Mourre (French), appointed by the Respondent. |
February 13, 2018 | The Tribunal holds a first session by telephone conference. |
February 28, 2018 | The Tribunal issues Procedural Order No. 1 concerning procedural matters. |
June 15, 2018 | The Claimants file a statement of claim. |
December 5, 2018 | The Respondent files a counter-memorial on the merits, a memorial on jurisdiction, and counterclaims. |
April 3, 2019 | The Claimants file a statement of reply. |
August 2, 2019 | The Respondent files a rejoinder on the merits, and a reply on jurisdiction and counterclaims. |
October 11, 2019 | The Claimants file a rejoinder on jurisdiction and counterclaims. |
November 25, 2019 | The President holds a pre-hearing organizational meeting with the parties by telephone conference. |
December 2, 2019 | The Tribunal issues Procedural Order No. 2 concerning the organization of the hearing. |
December 5, 2019 - December 13, 2019 | The Tribunal holds a hearing on jurisdiction and the merits in Washington D.C. |
March 27, 2020 | Each party files a post-hearing brief. |
April 17, 2020 | Each party files a submission on costs. |
December 17, 2020 | Case caption is updated following Claimants’ change of their legal company names from Gas Natural SDG, S.A. to Naturgy Energy Group, S.A. and from Gas Natural Fenosa Electricidad Colombia, S.L. to Naturgy Electricidad Colombia, S.L. |
March 12, 2021 | The Tribunal renders its award. |