Case Details
Grupo Energía Bogotá S.A. E.S.P. and Transportadora de Energía de Centroamérica S.A. v. Republic of Guatemala (ICSID Case No. ARB/20/48)
-
Electric power distribution project
-
Electric Power & Other Energy
-
FTA Colombia - El Salvador - Guatemala and Honduras 2007
-
ICSID Convention - Arbitration Rules
-
Grupo Energía Bogotá S.A. E.S.P. (Colombian), Transportadora de Energía de Centroamérica S.A. (Guatemalan)
-
Republic of Guatemala (Guatemalan)
-
November 3, 2020
-
White & Case, Mexico City, Mexico and Miami, FL, U.S.A.
-
Dechert, Paris, France
Dirección de Administración del Comercio Exterior, Guatemala City, Guatemala
Procuraduría General de la Nación, Guatemala City, Guatemala -
Pending
-
October 14, 2021 - The proceeding is resumed, pursuant to the parties’ agreement.
-
January 10, 2022
-
July 13, 2022
-
Eduardo SIQUEIROS T (Mexican) - Appointed by the Parties
-
Alexis MOURRE (French) - Appointed by the Claimant(s)
Ricardo RAMÍREZ HERNÁNDEZ (Mexican) - Appointed by the Respondent(s) -
White & Case, Mexico City, Mexico and Miami, FL, U.S.A.
-
Dechert, Paris, France
Dirección de Administración del Comercio Exterior, Guatemala City, Guatemala
Procuraduría General de la Nación, Guatemala City, Guatemala -
Pending
-
July 13, 2022 - A Consolidation Tribunal is constituted in accordance with Article 12.28 of the Free Trade Agreement between Colombia and El Salvador, Guatemala, and Honduras. Its members are: Eduardo Siqueiros (Mexican), President, appointed by agreement of the parties; Alexis Mourre (French), appointed by the Claimants; and Ricardo Ramírez Hernández (Mexican), appointed by the Respondent.
(a) Original Proceeding
Party Representatives
(b) Consolidation Proceeding
Composition of Tribunal
Party Representatives
No References Available.
(a) Original Proceeding
Date | Development |
---|---|
November 3, 2020 | The Secretary-General registers a request for the institution of arbitration proceedings. |
November 10, 2020 | The proceeding is suspended pursuant to the parties’ agreement. |
March 25, 2021 | The suspension of the proceeding is extended, pursuant to the parties’ agreement. |
October 14, 2021 | The proceeding is resumed, pursuant to the parties’ agreement. |
(b) Consolidation Proceeding
Date | Development |
---|---|
December 10, 2021 | The Claimants file a request for consolidation pursuant to Article 12.28(2) of the Free Trade Agreement between Colombia and El Salvador, Guatemala, and Honduras. |
December 20, 2021 | The Respondent files observations on the consolidation request. |
December 24, 2021 | The Claimants file additional observations on the consolidation request. |
January 5, 2022 | The Respondent files additional observations on the consolidation. |
January 7, 2022 | The Claimants file additional observations on the consolidation request. |
January 9, 2022 | The Respondent files additional observations on the consolidation request. |
January 10, 2022 | The Secretary General issues a decision on the request for consolidation pursuant to Article 12.28(3) of the Free Trade Agreement between Colombia and El Salvador, Guatemala, and Honduras. |
February 8, 2022 | Following appointment by the Claimants, Alexis Mourre (French) accepts his appointment as arbitrator. |
March 8, 2022 | Following appointment by the Respondent, Ricardo Ramírez Hernández (Mexican) accepts his appointment as arbitrator. |
July 13, 2022 | Following appointment by agreement of the parties, Eduardo Siqueiros (Mexican) accepts his appointment as presiding arbitrator. |
July 13, 2022 | A Consolidation Tribunal is constituted in accordance with Article 12.28 of the Free Trade Agreement between Colombia and El Salvador, Guatemala, and Honduras. Its members are: Eduardo Siqueiros (Mexican), President, appointed by agreement of the parties; Alexis Mourre (French), appointed by the Claimants; and Ricardo Ramírez Hernández (Mexican), appointed by the Respondent. |