Case Details
PT Ventures, SGPS, S.A. v. Republic of Cabo Verde (ICSID Case No. ARB/15/12)
-
Telecommunications concession
-
Information & Communication
-
BIT Cabo Verde - Portugal 1990
-
ICSID Convention - Arbitration Rules
-
PT Ventures, SGPS, S.A. (Portuguese)
-
Republic of Cabo Verde (Cabo Verdean)
-
April 14, 2015
-
September 15, 2015
-
Juan FERNÁNDEZ-ARMESTO (Spanish) - Appointed by the Parties
-
Fernando MANTILLA-SERRANO (Colombian) - Appointed by the Claimant(s)
Benfeito Mosso RAMOS (Cabo Verdean) - Appointed by the Respondent(s) -
Vieira de Almeida & Associados, Sociedade de Advogados, R.L, Lisbon, Portugal
-
Gide Loyrette Nouel A.A.R.P.I, Paris, France
J.G. Assis de Almeida & Associados, Rio de Janeiro, Brazil
José Manuel Gomes Andrade, Cidade de Praia, Cabo Verde
Oliver Melo Araújo, Cidade de Praia, Cabo Verde -
English,Portuguese
-
Concluded
-
June 10, 2019 -
The Tribunal issues a procedural order taking note of the discontinuance of the proceeding pursuant to ICSID Arbitration Rule 43(1).
(a) Original Proceeding
Composition of Tribunal
Party Representatives
(a) Original Proceeding
Published Decisions
Procedural Order No. 1
Procedural Order No. 2_PT
Procedural Order No. 3_PT
Procedural Order No. 4_PT
Order Taking Note of the Discontinuance of the Proceeding_PT
Available on the ICSID Website
Procedural Order No. 1 (November 30, 2015) English (Original)
Procedural Order No. 2_PT (November 1, 2018) Portuguese (Original)
Procedural Order No. 3_PT (November 16, 2018) Portuguese (Original)
Procedural Order No. 4_PT (November 30, 2018) Portuguese (Original)
Order Taking Note of the Discontinuance of the Proceeding_PT (June 10, 2019) Portuguese (Original)
(a) Original Proceeding
Date | Development |
---|---|
April 14, 2015 | The Secretary-General registers a request for the institution of arbitration proceedings. |
September 7, 2015 | Following appointment by the Claimant, Fernando Mantilla-Serrano (Colombian) accepts his appointment as arbitrator. |
September 8, 2015 | Following appointment by the parties, Juan Fernández-Armesto (Spanish) accepts his appointment as presiding arbitrator. |
September 15, 2015 | Following appointment by the Respondent, Benfeito Mosso Ramos (Cabo Verdean) accepts his appointment as arbitrator. |
September 15, 2015 | The Tribunal is constituted in accordance with Article 37(2)(a) of the ICSID Convention. Its members are: Juan Fernández-Armesto (Spanish), President, appointed by agreement of the parties; Fernando Mantilla-Serrano (Colombian), appointed by the Claimant; and Benfeito Mosso Ramos (Cabo Verdean), appointed by the Respondent. |
November 12, 2015 | The Tribunal holds a first session by telephone conference. |
November 30, 2015 | The Tribunal issues Procedural Order No. 1 concerning procedural matters. |
January 21, 2016 | The proceeding is suspended until April 20, 2016 pursuant to the parties’ agreement. |
March 23, 2016 | The suspension of the proceeding is further extended until June 11, 2016, pursuant to the parties’ agreement. |
June 6, 2016 | The suspension of the proceeding is further extended until September 11, 2016, pursuant to the parties’ agreement. |
September 20, 2016 | The suspension of the proceeding is further extended until December 11, 2016, pursuant to the parties’ agreement. |
December 12, 2016 | The suspension of the proceeding is further extended until February 11, 2017, pursuant to the parties’ agreement. |
June 23, 2017 | The Claimant files a memorial on the merits. |
October 23, 2017 | The Respondent files a counter-memorial on jurisdiction and the merits. |
February 1, 2018 | Following exchanges between the parties, each party files a request for the Tribunal to decide on production of documents. |
March 1, 2018 | The Tribunal issues a decision on production of documents. |
June 28, 2018 | The Claimant files a reply on the merits. |
August 27, 2018 | The Respondent files a rejoinder on the merits. |
September 28, 2018 | The President holds a pre-hearing organizational meeting with the parties by telephone conference. |
October 30, 2018 | The Claimant files a request for the Tribunal to decide on the admissibility of new evidence. |
November 1, 2018 | The Tribunal issues Procedural Order No. 2 concerning the organization of the hearing. |
November 11, 2018 | The Respondent files observations on the Claimant’s request of October 30, 2018. |
November 16, 2018 | The Tribunal issues Procedural Order No. 3 concerning the admissibility of new evidence. |
November 20, 2018 - November 21, 2018 | The Tribunal holds a hearing on jurisdiction and the merits in Paris. |
November 30, 2018 | The Tribunal issues Procedural Order No. 4 concerning procedural matters. |
March 27, 2019 | The proceeding is suspended until May 27, 2019, pursuant to the parties’ agreement. |
June 10, 2019 | The Tribunal issues a procedural order taking note of the discontinuance of the proceeding pursuant to ICSID Arbitration Rule 43(1). |